April 4th
Get emotive software installed and do a test run
Complete IRB Training
Lit review – what work has been done?
Install Sketchup and do a tutorial
April 11
Take Python training
Choose Google warehouse rooms to start from
Draft study design and questions
Draft IRBb
April 18
Test emotive + cave setup
Finish training on necessary skills
April 25
Finalize study design and questions
Finalize dates and times
Begin recruiting
May 2
Run tests
May 9
Iterate on test design if necessary
Begin writing report
May 16
Final polishing and submission
Contingency plan:
We’ve started with a fairly small core project design, leaving room to grow as time allows. If we experience problems, we’re actively logging possible avenues for assistance, including forums, DoIT technical training, and so on.